EDF Renewable Energy’s 150MW Merricourt wind project in the US state of North Dakota appeared in limbo after federal regulators declined to intervene following the termination of the project’s interconnection agreement by the grid operator. MISO, the grid operator in the central US, pulled the plug on Merricourt's interconnection agreement late last year when the developer missed its commercial operation deadline of 1 December 2015.