About 400MW worth of orders have already been officially confirmed, another 450MW have been confirmed to Recharge and 220MW are being negotiated now.

Confirmed orders include 129 machines or Dobreve Energia SA; 284 machines for Renova Energia SA; 18 machines for Bioenergy; and 100 machines for Contour Global. All machines will be the company’s 1.6MW turbine provided by its Campinas, São Paulo factory, which should start delivering turbines within two months, according to the source, who declined to be named.

The