It will transport, install and commission 17 of its G114-2.0MW turbines and eight of its G97-2.0MW machines at the Pisco wind farm in Portugal’s Guarda district.

It will deliver the turbines in the first half of 2015. The project will be completed by early 2016.

Gamesa has also agreed to build the wind farm’s underlying infrastructure, not including high-voltage connection lines.