The met-mast, installed by Spain's Drace Infraestructuras, will size up the resource blowing over the planned Telford, Stevenson and MacColl wind farms, for which the developer expects to install over 1.1GW of turbines.
Deployment of the met-mast, made up of a concrete caisson foundation, deck and 85-metre-tall lattice tower installed with a innovative telescopic hydraulic system rather than helicopters, represents the first infrastructure to be put in place on the site, located 22km offshore.
"This