The consortium has divided the connection process into six phases that will be implemented between 2015 and 2021, using four separate substations. Iberdrola says its global offshore development pipeline stands at 12GW and is being managed from its offshore business centre in Glasgow. The pipeline includes 9.5GW off the UK and 1GW in northern Europe, including the Wikinger offshore wind complex in the German zone of the Baltic Sea.