CEZ says it has complied with all the legal requirements needed to complete its €1.1bn ($1.4bn), 600MW wind farm, but work has been stopped by local officials accusing the company of not having all the necessary construction permits.

A CEZ official tells Recharge that the setback “is a continuation of local disputes”.

“We have already prepared legal steps to ensure continuations of the construction works,” she says, adding: “The commissioning of the second phase in the schedule is not affected.”