The three vendors together had 99% of US first quarter installations totaling 520MW with Vestas registering 150MW and General Electric 62MW, according to AWEA’s Q1 2016 Market Report.

On 31 March, projects under construction that have declared turbine OEM preference or signed supply contracts, Vestas is the leader with 2.965GW with GE second (2.375GW).

Far behind are Siemens (406MW), Gamesa (348MW) and Acciona (123MW).