Dutch government sets out schedule for Borssele 3&4 bidding

After its recent tender for the 700MW Borssele 1&2 area achieved the cheapest power price ever auctioned off in offshore wind, the Dutch government has said it will open the next tender for the nearby Borssele 3&4 area of about the same size on 15 September.

The Netherlands' first big offshore wind farm, the 108MW Egmond aan Zee
The Netherlands' first big offshore wind farm, the 108MW Egmond aan Zee
Published 12 July 2016, 15:45Updated 13 December 2016, 09:08