Major concerns were raised as the new wind farms were due to start providing power by January 2013, but the government-led grid connections, known as ICGs, were not going to come on line until September 2013.

Developers were originally meant to find alternatives to link their wind farms to the grid while the ICGs remained under construction, or pay fines and for the electricity owed under contract.

But