Borkum Riffgrund turbine delay

Danish developer Dong Energy said it is running "several months behind" on its 312MW Borkum Riffgrund 1 wind project off Germany after manufacturing issues caused delays to delivery of its Siemens turbines.

Foundations at Borkum Riffgrund await the arrival of their turbines
Foundations at Borkum Riffgrund await the arrival of their turbines
Published 20 August 2014, 12:09Updated 27 September 2016, 06:22