World's first twin-rotor floating wind turbine set for sea-trials

Part-scale W2Power unit to start fast-track programme at PLOCAN test centre in Atlantic

The world's first twin-rotored floating wind turbine has been moored and hooked up at a testing site in the Atlantic Ocean off the Spanish island of Gran Canaria.

The 1:6 scale W2Power prototype, built at the Astican shipyard in Las Palmas, will be trialed over the coming months at the PLOCAN marine testing centre by a development consortium led by EnerOcean.

“[With installation this unit] becomes the first Spanish floating wind platform at sea and confirms its objective to be the most cost efficient floating wind platform solution by reaching this important milestone at a fraction of the development and installation cost of other platforms currently at sea,” EnerOcean president Pedro Mayorga told Recharge.

The 40-tonne prototype, which will fly two “generic” 100kW-class machines on out-leaning towers, has a shallow-draft design that can be adjusted to get in and out of harbour. At full-scale, the W2Power platform is conceived of for a “sweet spot” of water-depths ranging from 35-300 metres.

Floating wind power plays the generation game

Read more

The W2Power concept, which has gone through several incarnations since first being introduced to the market in 2009 as a hybrid offshore wind-wave power design, is engineered to support a pair of “off the shelf” 6MW turbines, giving each unit a 12MW nameplate capacity.

Once the W2Power prototype is field-proven, EnerOcean aims to build a 3-5 unit development of up to 60MW, dubbed CanArray, off the Canaries, that could produce power at €100/MWh ($113/MWh). Commissioning of the project, expected to cost €140-€170m, could be as early as 2021.

Jan Erik Hanssen, part of the project team that devised the W2Power concept and co-founded EnerOcean, said he expected the W2Power technology to be “clearly positioned as a front runner” for the 50MW pre-commercial area of the 200MW floating wind tender expected to be launched soon by the Canaries government.

Earlier this month, Norwegian energy giant Equinor secured a permit to build a 200MW floating wind farm off the Canaries, which according to the regional government could start operations as early as 2024 if further regulatory hurdles are overcome this year.

Read Next


Next wave of floating wind begins to build

IN DEPTH | First-generation designs will break the nascent market open globally, but will have competition from new-look concepts also angling at a sub- €50/MWh cost of energy before 2030, writes Darius Snieckus

23 Apr 15:36 GMT

Latest