The Otary Group has completed the installation of all 42 turbines at the 309MW Rentel offshore wind farm about 40km north of Ostend in the Belgian part of the North Sea.

A2Sea’s jack-up installation vessel Sea Installer has over the weekend completed the installation of the 42 Siemens Gamesa SWT-7.0-154 turbines.

The full commissioning of the Euro1.1bn