The joint venture project is an operational 35 megawatt (MW) wind farm, which completed construction in January 2009. The financing is in addition to that announced in January 2009 and is debt based.
The facility’s phase I consisted of 10 wind turbines with a unit production capacity of 850kW each, Phase II will double the capacity and final third phase comprises 12 turbines with a unit production capacity of 1500kW each.