First Westermost monopile in place

The Siemens 6MW turbine at Hunterston

Westermost Rough will use the Siemens 6MW turbine

The first foundation was installed today at the 210MW Westermost Rough offshore wind farm in the UK North Sea, said developer Dong Energy.

The first of 35 monopiles was put in place by installation vessel GeoSea Innovation.

The foundations will support the wind farm’s 6MW Siemens offshore wind turbines when they go in later this year – the first major commercial deployment of the new machine.

Construction is being managed out of the east of England port of Grimsby.

Duncan Clark, Westermost Rough's programme director said: “This is a significant point on the project, and the first foundation installed really kicks off a critical time for construction.