Denmark sets out offshore tender schedule

Anholt will be fully operational by the end of the year

Anholt will enter service this year

Denmark has unveiled its schedule for 1.5GW of offshore wind tenders, including the 400MW Horns Rev 3 and 600MW Kriegers Flak developments, as it prepares to start talks with potential bidders this year.

As anticipated, the grid-connection date for Kriegers Flak has been pushed back to July 2018 as a result of the need to balance additional offshore wind with a surge of new PV capacity in Denmark.

The connection date for Horns Rev 3 is set earlier at January 2017, however.

The tender for Horns Rev 3 is expected to be awarded by early 2015, but bidders for Kriegers Flak will have to wait until the second half of that year to find out who is successful, according to a preliminary timetable issued…