"The substation was developed and built within a 16 month time frame by our contractor Bladt Industries, a steel construction company, together with the Danish subcontractors Semco and ISC," said Matthias Esken, project manager for the transformer substation at Nordsee Ost.

"We are now going to connect the substation with the previously installed inner-array cables and the TenneT export cables which remain to be installed."