As anticipated, the grid-connection date for Kriegers Flak has been pushed back to July 2018 as a result of the need to balance additional offshore wind with a surge of new PV capacity in Denmark.

The connection date for Horns Rev 3 is set earlier at January 2017, however.

The tender for Horns Rev 3 is expected to be awarded by early 2015, but bidders for Kriegers Flak will have to wait until the second half of that year to find out who is successful, according to a preliminary timetable issued by the Danish Energy Agency (DEA).

The