Riffgat was completed on time last July for utility EWE – but will only get its grid connection this week.

TenneThas faced criticism in Germany over delays to the connection of the 108MWRiffgat and other offshore wind farms, but said the scale of the challenge toremove World War 2 munitions was far greater than it had been led to believe, as a total of 30 tonnes of debris had to be cleared.