Foundations in at Dong's UK test site for Siemens 6MW turbine

Work at Dong Energy’s Gunfleet Sands offshore demonstration project has moved into its second phase following installation of the monopiles and transition pieces for its two 6MW Siemens turbines, which will be erected next year.

Located alongside the Danish group's 172MW Gunfleet Sands 1 and 2 developments off southeast England, Gunfleet Sands 3 is designed to test Siemens’ highest-capacity turbine.

The machines will stand 148-metres tall and feature 120-metre-diameter rotors, and the deployment will trial a range of installation and construction methods expected to help cut the cost of offshore wind.

“These will be the first two turbines of their kind to be installed offshore in the world,” says Dong Energy Wind Power’s UK country manager Benj Sykes.

“Crucial tests that we will conduct during the next three years…