Update: Forewind's plan of attack for Dogger Bank projects

Forewind, the consortium developing Dogger Bank, has mapped out the location of its first three wind farms, offering a glimpse into how Round 3 projects may unfold.

Licensed for 9.2GW of capacity, Dogger Bank has a significant size advantage over the second largest Round 3 project, the 7.2GW Norfolk zone being developed by Vattenfall and Scottish Power.

But Dogger Bank is seen as the most challenging Round 3 zone to develop, given its immense size and distance from shore.

Forewind – comprising RWE, Scottish and Southern Energy, Statoil and Statkraft – says it will carve up Dogger Bank into four tranches to ensure the project is “managed effectively and to evenly distribute the demand on those involved – from stakeholders…