Delivery schedules for the turbines (all 2MW) are as follows:

Hereford I, 100MW - Deliveries expected to begin in fall 2014 with commissioning in early 2015. Lincoln Renewable Energy is the project developer and EDF Renewable Energy is the asset owner.

Keechi, 110 MW - Deliveries expected to begin in summer this year, with commissioning in early 2015. RES Americas is the project developer and Enbridge is the asset owner.