The new schedule is based on informationfrom federal power company, Chesf, which said that the Caetité transmission lineand the Igapor substation will not be ready until then.

The wind farms for which Renova soughtpostponement of commercial operations are: Espigão with 10.8MW installedcapacity, Caetité with 30.2MW, Serra do Espinhaço with 18.5MW, Borgo with20.2MW, Pilões with 30.2MW, Ametista with 28.6MW, Maron 30.2MW, Pelourinho21.8MW