Gamesa willbuild the Dos Arbolitos wind farm in Juchitán deZaragoza in the state of Oaxaca, and equip it with 35 of its 2MW wind turbines.

Commissioning of the plant is due sometimein 2014, says Gamesa, which has some 544MW under development in Mexico.

The wind equipment group says the salefalls under its strategy of acting as “key development partner” at all stagesof a wind project.