Campos dos Ventos II was completed andhas been ready to start operations since September 2013.

Ithas been standing idle, along with the Santa Clara wind power complex, becauseof a lack of grid connections, which were completed late last month byfederal power company Chesf.

CPFL Renováveis also confirmed that the188MW Santa Clara Complex, including Eurus VI, has started pre-commercial testsand will start operations by March 30.