It recently emerged that the government's energy supply monitoring committee (CMSE) agreed this spring to begin sending out formal communiques to developers, emphasizing the need to stick to project deadlines.

The decision was taken after the CMSE digested data showing that of 112 wind projects being monitored, nearly half – or 54 – are behind schedule.

Just 22 are considered on-schedule, with the remainder – or 36 projects – having been finished this April.

Of