As part of its prior approval for the fully permitted project, AUC had required it to be in full commercial operation by the end of this year.

BlueEarth sought the delay to allow ATCO Electric to obtain AUC approval to construct the transmission infrastructure between a connection with the Alberta Integrated Electrical System and the project in southern Alberta, BluEarth spokeswoman Ameera Shivji tells Recharge.

The