The developer says that the Siemens 2.3MW turbines will be fully operational in August. The nacelles were manufactured in the US state of Kansas and the blades in the state of Iowa.

“The winter in Alberta was particularly harsh this year and created enormous challenges for our contractors, with temperatures regularly between -35 and -20 C. Despite this, the project is still on track to achieve completion on schedule,” says Gary Swan, head of construction for Mainstream.

Alberta