REpower installed 20 turbines, or 15% of the total, while troubled manufacturer/developer BARD installed 4 units.

Siemens was responsible for 74% of the total capacity added, against REpower’s 22% and BARD’s 4%.

During the six-month period, Europe installed and connected to the grid 532MW, up 50% on the same period in 2011.

The new capacity came at Belgium’s Thornton Bank 2; Greater Gabbard, Walney 2, Ormonde, London Array, Sheringham Shoal – all in the UK – ; Avedore in Denmark; and BARD Offshore 1 in Germany.