American Electric Power (AEP) expects to learn the fate of its 2GW Wind Catcher project by the end of June, later than it had hoped, although chief executive Nicholas Akins insists the wind farm could still be built in time to meet the production tax credit’s (PTC) deadline.

Having told investors earlier this year that AEP wanted to be in a position to make a final decision on the $4.5bn