US Geothermal Nevada plant starting operation this month

Developer US Geothermal expects to complete commissioning of its new 8.6MW net capacity plant in Nevada this month after replacement of two large capacitors that were found to be defective in January, chief executive Daniel Kunz tells Recharge.